BUILDER-TO-SOCIETY HANDOVER LETTER AND CHECKLIST
Date: 7 April 2026
From: Sunrise Developers Private Limited, a company incorporated under the Companies Act, 2013, having its office at X (the "Promoter")
To: The Managing or Governing Committee, Sunrise Meadows Co-operative Housing Society Limited, a co-operative housing society registered under the Maharashtra Co-operative Societies Act, 1960, bearing registration number X dated 2 April 2026, having its registered address at X (the "Society")
Subject: Handover of documents, plans, common areas, accounts, deposits and warranties in respect of Sunrise Meadows Phase I — section 17(2) of the Real Estate (Regulation and Development) Act, 2016
1. THE PROJECT
1.1 This letter concerns the real estate project known as Sunrise Meadows Phase I, situated at X in Maharashtra, developed on the land described as: All that piece of land bearing CTS No. 412/3, Village Wadgaon Sheri, Taluka Haveli, admeasuring 6,240 square metres (the "Project").
1.2 The Project comprises 25,000 apartments together with the common areas and facilities serving them.
1.3 The occupancy certificate for the Project is: Full Occupancy Certificate No. PMC/BP/OC/1123 dated 14 March 2025.
1.4 The Project is registered with the Real Estate Regulatory Authority for Maharashtra under registration number P52100012345.
2. BASIS OF THIS HANDOVER
2.1 Under section 11(4)(e) of the Real Estate (Regulation and Development) Act, 2016 (the "Act") the Promoter is obliged to enable the formation of the association or society of allottees. The Society has been formed and registered as recorded above.
2.2 Under section 17(1) of the Act the Promoter is obliged to execute a registered conveyance of the apartment in favour of each allottee, together with the undivided proportionate title in the common areas in favour of the Society, and to hand over physical possession of the common areas to the Society.
2.3 Under section 17(2) of the Act, after obtaining the occupancy certificate and handing over physical possession to the allottees, the Promoter is responsible for handing over the necessary documents and plans, including in respect of common areas, to the Society as per the local laws.
2.4 This letter and the checklist at Schedule A are issued in performance of those obligations. This letter does not operate as a conveyance and does not by itself transfer any right, title or interest in the land or in the structure of the Project.
3. PART A — HANDOVER BY THE PROMOTER
3.1 The Promoter hereby hands over to the Society, with effect from 1 April 2026, physical possession of the common areas and facilities of the Project, together with the documents, plans, certificates, approvals, warranties, contracts, keys, deposits and records itemised in Schedule A.